If the charterer delayed the ship beyond the lay days, he is asked to pay

If the charterer delayed the ship beyond the lay days, he is asked to pay
  • A.
    dead freight
  • B.
    demurrage
  • C.
    lump sum
  • D.
    freight
Correct Answer: Option B
Explanation